Schedule of works planner

See how a refurb usually runs before you ask for quotes. Pick the type of project, its size and the phases it needs to get an example timeline and a budget split by phase. Every figure is an example to plan with, not a price.

Your project

A tired house brought up to a lettable or saleable standard: rewire, heating, kitchen, bathroom, plaster.

The example figures are written for 85 m² and scale with the size.

Phases

Untick the phases your project doesn't need.

Results

Example plan

Example figures
Programme
7 weeks
35 working days
Estimate
£37,400
14 tasks
Contingency
£5,610
15% of the estimate
Budget
£43,010
Estimate plus contingency

Budget split by phase

  • Strip-out£3,100 (8%)
  • Structural£2,600 (7%)
  • First fix£7,200 (19%)
  • Plastering£4,200 (11%)
  • Second fix£12,900 (34%)
  • Decoration£5,000 (13%)
  • External£1,800 (5%)
  • Snagging£600 (2%)

Example tasks, durations and costs for planning, not quotes or supplier prices. Get at least three quotes from builders you have checked, and keep the contingency until the work is signed off.

Example timeline

Starting Monday 2 November 2026, finishing 18 December 2026

Example timeline for a full refurb14 tasks over 35 working days (7 weeks) from 2 Nov. Each task's dates are in the task table.W12 NovW29 NovW316 NovW423 NovW530 NovW67 DecW714 DecStrip-outStrip kitchen, bathroom, floor coverings and old plaster: day 1 to 4, Not startedStrip kitchen, bathroom…Skip hire and waste: day 1 to 1, Not startedSkip hire and wasteStructuralDamp proofing and replace a rotten joist: day 5 to 7, Not startedDamp proofing and repla…First fixFull rewire, first fix: day 8 to 12, Not startedFull rewire, first fixCentral heating and plumbing, first fix: day 8 to 12, Not startedCentral heating and plu…PlasteringBoard ceilings and skim walls: day 13 to 20, Not startedBoard ceilings and skim…Second fixFit kitchen: day 21 to 24, Not startedFit kitchenFit bathroom: day 21 to 24, Not startedFit bathroomElectrics and heating, second fix and certificates: day 21 to 23, Not startedElectrics and heating, …Internal doors, skirting and architrave: day 21 to 24, Not startedInternal doors, skirtin…DecorationDecorate throughout: day 25 to 30, Not startedDecorate throughoutFlooring throughout: day 31 to 33, Not startedFlooring throughoutExternalRepoint the front and fix gutters: day 1 to 3, Not startedRepoint the front and f…SnaggingSnag, builder's clean and handover: day 34 to 35, Not startedSnag, builder's clean a…
  • Not started
  • Booked
  • In progress
  • Done
  • Waits for

Inside phases follow one another; external works run alongside from the first day. Weekends are left out, bank holidays and weather are not.

Plan the real job in the app

The schedule of works planner adds tasks you can edit, contractors from your power team, payment stages tied to bridging drawdowns, a snagging list and a refurb figure you can send to the Deal Stacker.

Open the planner

Early access

Run this on real deals. Automatically.

Yieldhouse runs these numbers for you on the deals you forward or paste, with a valuation range and a Deal Score on each one. Join the waitlist for early access.

Free to join. Unsubscribe in one click.

No spam. We’ll only email you about Yieldhouse early access.